2006 Prudhoe Bay Shutdown: Will Recent Regulatory Changes and BP

Other Related Documents:
Comm on Energy & Commerce BP Hearing
May 16, 2007

You can view and download the Hearing and testimony

HEARING
http://energycommerce.house.gov/cmte_mtgs/110-oi-hrg.051607.Prudhoe.Bay.shtml

Subcommittee on Oversight and Investigations
Wednesday, May 16, 2007, 9:30 a.m.
2123 Rayburn House Office Building
http://energycommerce.house.gov/cmte_mtgs/110-oi-hrg.051607.Prudhoe.Bay.shtml

Other Related Documents:

BP America Inc. Final Report (Booz Allen Hamilton)  11.2 MB
http://energycommerce.house.gov/Investigations/BP/Booz%20Allen%20Report.pdf

Investigation exhibits and reports 4.19 MB ( 31 documents )
Names listed below
http://energycommerce.house.gov/Investigations/110-oi-hrg.051607.InvestigationsBinder.shtml

U.S. Chemical Safety & Hazard Investigation Board
Investigation Report 5.37 MB
http://www.csb.gov/completed_investigations/docs/CSBFinalReportBP.pdf

Redacted Interim Report of Investigation 2.28 MB
http://energycommerce.house.gov/Investigations/BP/Billie%20Garde%20on%20Failure%20to%20Disclose.pdf

Veco Report — 7.5 MB
http://energycommerce.house.gov/Investigations/BP/Veco%20Report.pdf

PBU – Management of Change — 700 KB
http://energycommerce.house.gov/Investigations/BP/PBU%20-%20Management%20of%20Change.pdf

Exhibits

Exhibit #  DESCRIPTION DATE

1
Internal Correspondence on Inspection of Oil Sales Lines 6/5/1990
http://energycommerce.house.gov/Investigations/BP/Exhibit.1.pdf

2
Email on “Oil Transit Pigging” from PBU, CIC Flow Lines 7/17/1997
http://energycommerce.house.gov/Investigations/BP/Exhibit.2.pdf

3
Email Reply on “Smart Pigging of oil transit line” from PBU, CIC Flow Lines 7/27/1997
http://energycommerce.house.gov/Investigations/BP/Exhibit.3.pdf

4 pg. 1
Email Reply on “Draft – Budget Review 1 Pager” from Richard Woollam 6/2/1999
http://energycommerce.house.gov/Investigations/BP/Exhibit.4.pdf

4 pg. 2
Email Reply on “PW inhibitor at GC2 and GC3” from PBU, CIC NS TL Felix/Phillips 6/4/1999
http://energycommerce.house.gov/Investigations/BP/Exhibit.4.pdf

4 pg. 4
Email Reply on “MOC for Discontinuation of EC1081A” from PBU, CIC Prod Chem Todd/Spano 6/8/1999
http://energycommerce.house.gov/Investigations/BP/Exhibit.4.pdf

4 pg. 6
Email Reply on “PW Inhibitor at GC2 and GC3” from PBU, Operations Manager 6/9/1999
http://energycommerce.house.gov/Investigations/BP/Exhibit.4.pdf

5
Email Reply on “Urgent – Please Review and Comment” from Exxon to BP 6/9/1999
http://energycommerce.house.gov/Investigations/BP/Exhibit.5.pdf

6
Email Reply on “APC Budget” from Richard Woollam to Bob Malone 3/8/2000
http://energycommerce.house.gov/Investigations/BP/Exhibit.6.pdf

7
Preliminary 2001 Budget from CIC Town Hall Jan-01
http://energycommerce.house.gov/Investigations/BP/Exhibit.7.pdf

8
Email on “Smart Pigging of Oil Sales Lines” from Richard Woollam 1/7/2001
http://energycommerce.house.gov/Investigations/BP/Exhibit.8.pdf

9
Email Reply on “Smart Pigging of Oil Sales Lines” from Kip Sprague 1/8/2001
http://energycommerce.house.gov/Investigations/BP/Exhibit.9.pdf

10
Email Reply on “CIC Group Team Leader Meeting – 21st May” from Nancy Foust
5/14/2001
http://energycommerce.house.gov/Investigations/BP/Exhibit.10.pdf

11
Email Reply on “CIC Group Team Leader Meeting – 21st May” from Richard Woollam 5/14/2001
http://energycommerce.house.gov/Investigations/BP/Exhibit.11.pdf

12
Email Reply on “CIC Group Team Leader Meeting – 21st May” from PBU, CIC NS TL Felix/Phillips 5/16/2001
http://energycommerce.house.gov/Investigations/BP/Exhibit.12.pdf

13
Email Reply on “ACTION: 2001 Year End Forecast” from Nancy Foust 10/15/2001
http://energycommerce.house.gov/Investigations/BP/Exhibit.13.pdf

14
Email on Budget Reduction 10/16/2001
http://energycommerce.house.gov/Investigations/BP/Exhibit.14.pdf

15
Email on “Removal of additional corrosion inhibitor” from NSU, CIC TL 10/16/2001
http://energycommerce.house.gov/Investigations/BP/Exhibit.15.pdf

16
Spreadsheet on “CIC Group 2002 Budget Challenge – $1 Million Opportunities”  undated
http://energycommerce.house.gov/Investigations/BP/Exhibit.16.pdf

17
Email Reply on “Master ID 2996 GPB Pig Launcher and Receiver Prelim Engineering” from C Drais Farnham  2/5/2003
http://energycommerce.house.gov/Investigations/BP/Exhibit.17.pdf

18
Forwarded Email on “ACTION: 2003 August LE’s and Field OVERVIEW” from NSU, CIC TL 12/7/2003
http://energycommerce.house.gov/Investigations/BP/Exhibit.18.pdf

19
Slide on “Opportunity to Make Stretch Budget”  undated
http://energycommerce.house.gov/Investigations/BP/Exhibit.19.pdf

20
Spreadsheet on “Greater Prudhoe Bay/2004 Field Lifting Cost Challenge (LCC) Maintenance and Reliability”  2/5/2003
http://energycommerce.house.gov/Investigations/BP/Exhibit. 20.pdf

21
Email Reply on “Cost Challenge Feedback” from Richard Woollam 4/16/2004
http://energycommerce.house.gov/Investigations/BP/Exhibit.21.pdf

22
Letter from Tower Petroleum Corporation to Northwest District Debarment Council 5/8/2004
http://energycommerce.house.gov/Investigations/BP/Exhibit.22.pdf

23
Email Reply on “Emailing: CIC MR-Capex AFE Tracker 2006.xls” from Kip Sprague 4/10/2005
http://energycommerce.house.gov/Investigations/BP/Exhibit.23.pdf

24
Email on “Emailing: Control Options 10 22 05.xls” with attachment from NSU, CIC TL  10/22/2005
http://energycommerce.house.gov/Investigations/BP/Exhibit.24.pdf

25
Email Reply on “GC-2 Oil Transit Line Spill” from John Dengler 3/9/2006
http://energycommerce.house.gov/Investigations/BP/Exhibit.25.pdf

26
Email Reply on “Pigging Facility Walk Down – Need your input on Pigging Concerns” from GPB, FS2 Ops Lead 3/23/2006
http://energycommerce.house.gov/Investigations/BP/Exhibit.26.pdf

27
Email Reply on “Sales Oil Pipeline Protection” from NSU, CIC Prod Chem (Nalco) 6/4/2006
http://energycommerce.house.gov/Investigations/BP/Exhibit.27.pdf

28
Correspondence Regarding Oil Spill and Subsequent Investigation 08/31/06 – 05/14/07
Missing

29
Chart on Themes Highlighted in Various Reports on BP undated
http://energycommerce.house.gov/Investigations/BP/Exhibit.29.pdf

30
Article on “BP admits knowing of corrosion problems: Workers had predicted ‘major catastrophic event’ because of cost-cutting” 8/9/2006
http://energycommerce.house.gov/Investigations/BP/Exhibit.30.pdf

31
Notes from “CIC Strategy & Planning” Interview of Bill Hedges by Tom Williams in Anchorage, AK 12/14/2006
http://energycommerce.house.gov/Investigations/BP/Exhibit.31.pdf

~ by fredfelleman on May 19, 2007.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

 
%d bloggers like this: